Downtown Bellevue is about to see a few major road closures due to construction of the East Link light rail project. So make sure you plan ahead and give yourself extra time. Here's a snapshot of the what, where, and when. Want to avoid the construction altogether? Try a different route. ChooseYourWayBellevue.org is a great local resource to plan your commute.  

July Closures:

  • Now – July 2
    • One lane of traffic going North-South\
  • July 21 – Fall 2019
    • Full closure of 110th Ave NE

110th Closure

 

August Closures:

August 9 at 10 pm – August 11

  • Off-ramps to NE 4th St
  • On-ramps from NE 8th St to southbound I-405 
  • From 8 pm – 5 am, one right lane going from NE 10th to NE 4th 

August 11 – August 12 at 5 am

  • Southbound mainline lanes 
  • Northbound I-405 HOV off-ramp
  • HOV on-ramp to I-405 northbound from NE 6th St
  • Southbound I-405 off-ramps to NE 4th St
  • Eastbound NE 8th St on-ramps to southbound I-405

August 16 at 10 pm – August 18

  • One right lane on northbound I-405 from NE 8th to Main St
  • Northbound I-405 off-ramp to NE 8th St
  • On-ramp from NE 4th St to northbound I-405

August 18 – August 19 at 5 am

  • Northbound I-405 mainline lanes
  • Northbound I-405 HOV off-ramp 
  • NE 6th St southbound HOV on-ramp
  • NE 4th St to northbound I-405 on-ramp